The RFQ checklist: what you need before quotes become comparable

Non-comparable quotes are usually an input problem, not a supplier problem. Here is the minimum and the recommended data set per category.

6 min read · 2026-08

Four items every category needs

Whatever the part, missing any of these four distorts the quotation — and the difference comes back later as an engineering change or a price increase.

  • Annual volume and batch size (EAU and minimum order quantity)
  • Target price or current benchmark (a range is fine)
  • Applicable standards and acceptance method (IATF, customer-specific requirements)
  • Packaging, labelling and delivery term (EXW / FOB / DDP)

PCBA / EMS package

Electronics quotes are dominated by the bill of materials, so BOM discipline decides comparability.

  • Gerber or ODB++ files, stack-up and impedance requirements
  • BOM with manufacturer part numbers, marking which items allow alternates
  • Pick-and-place coordinates and silkscreen requirements
  • Test requirements: ICT / FCT / programming / burn-in, and who owns the fixtures
  • Traceability: serial numbers, barcodes, batch records

Harness and connector package

Harness cost is terminals, housings and labour; connector alternatives need validation evidence on top.

  • Harness drawing with lengths, branches, housings and tie positions
  • Terminal and housing part list, or the original numbers to be substituted
  • Wire gauge, colour code and temperature class
  • Impedance, insertion loss and return loss targets for RF links
  • Installation space and routing constraints

Tooling and BLDC motor package

Structural parts and motors are quoted off the model and duty cycle; missing either forces a range price.

  • 3D model (STEP) and 2D drawing with critical dimensions and datums
  • Material grade or performance requirement (temperature, flammability, UV)
  • Cosmetic class and surface finish
  • Tool life, cavity count and tool ownership terms
  • Motor: torque, speed, voltage, interface dimensions and noise limits

When the package is incomplete

A complete package is rare in practice. We reverse-engineer from samples or existing parts, issue a preliminary quotation with the assumptions written out, and flag which prices will move once data is complete — rather than pushing a low number that will not hold.

Document FAQ

Can we quote from a physical sample only?
Yes. We produce a reverse-engineered drawing and preliminary BOM from CMM measurement and material identification. It adds 1–2 weeks but makes the resulting quotes comparable.
Do brands have to be specified in the BOM?
For critical devices yes, with alternates explicitly allowed or forbidden. Generic passives can stay open — that is usually where the cost headroom is.
Do we need an NDA before sending data?
We recommend a mutual NDA before drawings and BOMs are shared, and we impose the same obligation on the supplier side.